The community park is moving along! Below are a few key deliveries that have been achieved and are happening this month:
- Climbing Wall
- The rebar inspection for the large playground wall passed last Friday.
- Restroom
- Restroom permit was acquired.
GoodLand over-excavated the site and has been working on the restroom foundation. - The restroom was built offsite and is scheduled to be delivered and installed next week on Wednesday, May 22nd.
- The restroom will have running water and a flush toilet.
- Restroom permit was acquired.
- Playground Signs
- Architerra is working with Artcraft on the fabrication of the signs.
- The signs will tie into the theme and will also include park rules and a community board.
- Sculptures
- The sculptures for the park were scheduled to be here in June however the company providing them is now quoting closer to August.
- There is a 4-6 week lead time on the customized sculptures.
- Site Furnishings
- All site furnishings have been ordered and will be stored at Goodland’s site until ready to be installed.
- Shelter
- We have received the engineering drawings for the shelter.
- Playground Equipment
- The equipment has been ordered and is shipping in May.
- The large spinner (pictured below) has been ordered and shipped.
Shown above is a picture of the large spinner that was ordered for the playground.
Thank you to our community for your support of this project!